Party wall guide

What is a Party Wall Award and what’s in it?

A Party Wall Award is the legal document surveyors make when a building owner and an adjoining owner are in dispute under the Party Wall etc. Act 1996. It settles whether, how and when notifiable work can be done, records the neighbour’s property, and decides who pays. This guide explains what goes into an Award, how it is made and served, and what happens if someone disagrees with it.

CB

Written by Carl Brady MFPWS, MPTS

MFPWSMPTS

Party wall surveyor with 25+ years’ experience in party wall matters across the Midlands, Hertfordshire and London. Last reviewed 27 October 2026.

Short answer: A Party Wall Award is made under section 10 by an Agreed Surveyor or by two surveyors (with a third in reserve). It may determine the right to execute the work, the time and manner of executing it, and any other matter arising from the dispute, including costs (s.10(12)). It is conclusive and binding on both owners unless appealed to the county court within 14 days of service (s.10(16)–(17)).

When an Award is needed

An Award is needed whenever a dispute arises or is deemed to arise: the neighbour dissents from a section 3 or section 6 notice, or does not consent within 14 days (s.5, s.6(7)), or a dispute arises under section 1 (s.1(8)). It is also used to settle later disputes, for example about damage or costs, even where the neighbour originally consented. If the neighbour consents in writing, no Award is needed.

Who makes it

Either an Agreed Surveyor acting alone, or the three surveyors or any two of them (s.10(10)). In a two-surveyor case, the two party-appointed surveyors normally agree and sign it; the third surveyor makes an Award only if called upon (s.10(11)). The surveyors can only settle matters “connected with any work to which this Act relates” and in dispute between the owners. They cannot decide boundary disputes or planning matters.

What a typical domestic Award contains

Part of the AwardWhat it does
RecitalsNames the owners and properties, the notices served, the dispute and the surveyors appointed
Description of worksDefines exactly what the building owner may do, by reference to drawings
Drawings and detailsArchitect’s and engineer’s drawings and calculations, which the work must follow (s.7(5))
Schedule of ConditionThe record of the neighbour’s property, annexed
Method and protectionHow critical elements are done (e.g. hand-cutting pockets, temporary support, roof weathering, dust and debris protection)
Time and mannerWorking hours, noisy-work restrictions, sequence, completion within a reasonable time
AccessArrangements for entry under s.8 if needed
Making goodDuty to make good damage, or pay in lieu (s.11(8)); compensation for loss (s.7(2))
SecurityAny security for expenses agreed or determined (s.12)
InspectionsSurveyors’ right of access to check the work (s.8(5))
CostsWho pays the surveyors’ reasonable costs (s.10(13)), normally the building owner

Timing rules built into the Act

Any period the Award sets for executing work does not begin to run until the statutory notice period has expired, unless the owners agree otherwise (s.10(12)). So an Award made quickly does not by itself let work start before the two months (or one month) are up.

Service

Where the party-appointed surveyors make the Award, they serve it on the owners “forthwith” (s.10(14)). An Award made by the third surveyor is served after payment of the costs of the Award (s.10(15)). The date of service matters, because the 14-day appeal period runs from it.

How binding is it?

The Award is conclusive and cannot be questioned in any court except by the statutory appeal (s.10(16)). Either owner may appeal to the county court within 14 days beginning with the day the Award is served on them; the court may rescind or modify it and make an order about costs (s.10(17)). Appeals are uncommon and should not be started without proper advice, because costs can quickly exceed the issue in dispute. See appealing a Party Wall Award.

An Award can be invalid if the surveyors had no jurisdiction: for example, if the notice was defective, an appointment was not properly made, or the Award strays into matters the Act does not cover. That is why the paperwork leading up to the Award matters.

Changes after the Award

Sites change. If the building owner needs to vary the work, for example a different beam position, the change must be agreed between the owners or their surveyors, or determined by the surveyors (s.7(5)). This is usually done by an addendum Award. Work that falls outside both the notice and the Award may need a fresh notice.

Worked example: what the Award does in practice

Illustrative only. The Award for Jack’s kitchen knock-through with a beam into the party wall sets out the engineer’s beam and padstone details; requires pockets to be cut by hand or with non-percussive tools; limits drilling into the party wall to 8am to 5pm on weekdays; requires dust sheets on the neighbour’s side during cutting; annexes the Schedule of Condition; provides for a final inspection; and orders Jack to pay the surveyor’s fee. When a hairline crack appears above the neighbour’s kitchen door, the surveyor compares it with the Schedule, confirms it is new, and the neighbour chooses a payment in lieu rather than having Jack’s builder return.

Award checklist for building owners

  • Give the surveyor complete drawings and engineer’s details early.
  • Share the Award with your builder before they start, and make sure they understand the working hours and method.
  • Do not change the design without telling the surveyor.
  • Keep the neighbour informed as work progresses.
  • Arrange the final inspection promptly.

Our fee

An Award is £400 + VAT on its own, or part of our full package of notices, Schedule and Award at £899 + VAT (£999 + VAT in London). Acting as Agreed Surveyor is normally a £50 supplement, currently waived.

Awards for damage and other later disputes

An Award is not only made before work starts. If damage occurs during or after the works and the owners cannot agree what is owed, the surveyors already appointed can make a further Award determining whether the damage was caused by the notified work and what should be done. The adjoining owner can require the cost of making good to be determined and paid to them instead of having the builder do the repair (s.11(8)). The Schedule of Condition annexed to the original Award is the key evidence. Likewise, disputes over security for expenses (s.12), access (s.8) or deviations from the agreed plans (s.7(5)) can each be settled by Award.

What an Award cannot do

  • Decide where the boundary is or who owns a wall.
  • Authorise work that was not covered by a valid notice or does not fall within the Act.
  • Grant planning permission or Building Regulations approval.
  • Override other legal rights unconnected with the notified work, such as rights of light.
  • Give a right to oversail the neighbour’s land with gutters or eaves.

Surveyors who stray outside their jurisdiction risk an invalid Award, which is why a careful surveyor keeps the Award tightly tied to the notice and the drawings.

Sources and further reading

Section references are to the Party Wall etc. Act 1996 as it applies in England and Wales, checked against legislation.gov.uk. This guide is general professional guidance, not legal advice; every project should be assessed on its own drawings.

Planning work? Take the 1-minute check, see our fixed fees or call free on 08000 487897. We have helped on 750+ projects.

Sources: Party Wall etc. Act 1996 (legislation.gov.uk) · The Party Wall etc. Act 1996: explanatory booklet (GOV.UK) · Faculty of Party Wall Surveyors (FPWS). Last reviewed 27 October 2026. General guidance on the law in England and Wales, not legal advice.

Frequently asked questions

Is a Party Wall Award the same as a party wall agreement?

It is one of the two things people mean by the phrase. The other is the neighbour’s written consent.

Can work start before the Award is served?

Where there is a dispute, the notified works should not start until the Award is in place and the notice period has passed (unless the owners agree otherwise in writing).

How long is an Award valid?

An Award relates to the notified works. If the notice lapses because work has not started within 12 months, a fresh notice, and possibly a fresh Award, will be needed.

Can I appeal against an Award?

Yes, to the county court, within 14 days beginning with the day it was served on you (s.10(17)). Take advice first.

Does an Award protect the building owner as well?

Yes. It confirms their right to do the work, and records the neighbour’s property so that only damage caused by the works is attributed to them.

Who pays for the Award?

The surveyors decide under s.10(13). For works solely for the building owner’s benefit, that is normally the building owner.

Is an Award registered on the property title?

No. It is not registered with the Land Registry, but buyers’ solicitors often ask for copies, so keep it with your property documents.

Can an Award cover damage that happens after the works?

Yes. Surveyors can make a further Award to settle disputes about damage arising from the notified works.

Can the surveyors award compensation as well as repairs?

Yes. The building owner must compensate for loss or damage resulting from the work (s.7(2)), and the adjoining owner can ask for a payment in lieu of making good (s.11(8)). The surveyors can determine the amount.