Consent vs consent with a Schedule vs dissent: your neighbour’s options

When you serve a party wall notice, your neighbour chooses how to respond, and that choice shapes your budget and your start date more than anything else. This guide sets out the four responses recognised in Faculty of Party Wall Surveyors (FPWS) guidance, what each involves under the Act, and how building owners can make the simplest suitable route the obvious one.

JG

Written by John Greenan AssocRICS, MFPWS, ACABE

AssocRICSMFPWSACABE

Party wall and residential property surveyor with 25+ years’ experience in surveying and construction. Last reviewed 27 October 2026.

Short answer: Your neighbour can (a) consent; (b) consent subject to a Schedule of Condition, our recommended and most popular route, which keeps the full protection of the Act for straightforward works; (c) dissent and concur in an Agreed Surveyor (s.10(1)(a)) where extra terms are needed; or (d) dissent and appoint their own surveyor (s.10(1)(b)), best for complex or contentious works. Every surveyor under the Act must act impartially, so no option gives “more protection” in itself.

The four options compared

OptionBest forWhat it involvesTypical cost to building owner (our fees + VAT)
a. ConsentVery minor works between neighbours who know each other wellA signed written consent. No record of the neighbour’s property, so later damage is harder to attribute.£150 (notices)
b. Consent with a Schedule of Condition (recommended, most popular)Most straightforward domestic works: lofts, beams, chimney breasts, extensionsConsent plus a dated photographic record. The building owner’s duties still apply, and if a problem arises later the dispute procedure is still available.£499 (notices + Schedule)
c. Agreed Surveyor AwardWhere the neighbour wants formal terms: working hours, access, protection, methodOne impartial surveyor acts for both owners and makes a full Award (s.10(1)(a)).£899 full package (£999 London)
d. Own surveyorComplex or contentious works: basements, underpinning, fragile structures, poor relationsEach owner appoints a surveyor; the two select a third and agree the Award (s.10(1)(b)).£899 (£999 London) plus the neighbour’s surveyor’s reasonable fees

These options follow FPWS guidance and the government’s explanatory booklet. The booklet makes the important point that where consent is given, the building owner is not relieved of their obligations under the Act, for example to avoid unnecessary inconvenience (s.7(1)) or to provide temporary protection for adjacent buildings (s.7(3)), and to make good or compensate for damage.

Option a: consent

The adjoining owner serves written notice of consent (s.3(3)(a)). No dispute arises, no surveyor is needed, and work can start when the notice period expires (or earlier if they also agree to that in writing). The weakness is evidential: if cracks appear after the works, nobody can easily show whether they were there before. That is why we rarely recommend plain consent except for very minor work.

Option b: consent with a Schedule of Condition

The neighbour consents on condition that a Schedule of Condition of their property is taken before the work starts. It costs little, takes 1 to 2 hours on site, and gives both sides the evidence they need. If damage arises, the comparison is straightforward and the building owner makes good. If a genuine disagreement arises later, a dispute can still be referred to surveyors under section 10. This is the route most of our clients’ neighbours choose, and the one we recommend for most domestic projects. See our Schedule of Condition guide.

Option c: Agreed Surveyor

If the neighbour wants a formal document setting out how the work will be done, both owners can concur in one Agreed Surveyor. The surveyor takes a Schedule, reviews the drawings and makes an Award covering the method, working hours, protection, access and making good. One surveyor means one fee and faster progress. The government booklet says that in residential cases where surveyors’ fees would significantly increase project costs, an Agreed Surveyor is preferable, especially if the surveyor is not otherwise involved in the project. Note that with an Agreed Surveyor there is no third surveyor; if the Agreed Surveyor cannot continue, the process begins again (s.10(3)).

Option d: own surveyor

The neighbour appoints a surveyor of their choosing, and the building owner has their own. The two select a third surveyor, who is called on only if they cannot agree (s.10(11)). This route suits complex or contentious works, or where the relationship has broken down. It costs the building owner more, because they normally pay both surveyors’ reasonable fees (s.10(13)), and it usually takes longer. It does not give the neighbour more legal protection than an Agreed Surveyor; both surveyors have the same statutory duty to act impartially.

What if the neighbour does nothing?

Silence for 14 days after a section 3 or section 6 notice means a dispute is deemed to have arisen (s.5, s.6(7)). The building owner then asks them to appoint, and if they still do nothing within 10 days, appoints a surveyor for them (s.10(4)). See the 14-day rule.

How building owners can make consent more likely

  • Talk to the neighbour before serving notice, ideally with the drawings in hand.
  • Explain the timetable, working hours and how the builder will protect their property.
  • Offer a Schedule of Condition at your cost.
  • Include a simple response form with the notice.
  • Answer questions quickly and honestly.

Worked example

Illustrative only. Ben’s notices for a rear dormer go to both neighbours. On the left, an elderly owner who has lived there for forty years is worried about her ornate ceilings; once she understands that a Schedule will record them and any damage will be put right, she consents with a Schedule. On the right, a landlord who lives abroad wants formal terms for the tenants’ benefit and agrees to an Agreed Surveyor. Neither appoints their own surveyor, and Ben’s builder starts on time.

For neighbours reading this

If you have received a notice, see our guide to consenting or dissenting and your options as an adjoining owner. You can also call us free on 08000 487897.

How each option affects your timetable

OptionEarliest startWhat can slow it down
ConsentEnd of the notice period, or earlier if the neighbour agrees in writingLittle
Consent with ScheduleAs above, once the Schedule is takenArranging access for the inspection
Agreed SurveyorEnd of the notice period, once the Award is servedIncomplete drawings; questions on method
Own surveyorEnd of the notice period, once the Award is agreed and servedTwo diaries, correspondence between surveyors, engineer’s queries

Any period an Award sets for doing the work does not begin until the statutory notice period has expired unless the owners agree otherwise (s.10(12)), so even a quick Award does not shorten the notice period.

Can a neighbour switch options later?

A neighbour who consents can still refer a later disagreement, about damage for example, to surveyors under section 10. A neighbour who has appointed a surveyor cannot rescind that appointment (s.10(2)), but the owners can still agree matters between them. In practice, we encourage both sides to choose the simplest option that suits the work at the start.

Questions neighbours often ask before choosing

Will I have to pay? Normally not, for works solely for the building owner’s benefit. Will a surveyor need to come in? Yes, for a Schedule or an Award, usually for 1 to 2 hours. Can I still object to the planning application? Yes, that is a separate process.

Sources and further reading

Section references are to the Party Wall etc. Act 1996 as it applies in England and Wales, checked against legislation.gov.uk. This guide is general professional guidance, not legal advice; every project should be assessed on its own drawings.

Planning work? Take the 1-minute check, see our fixed fees or call free on 08000 487897. We have helped on 750+ projects.

Sources: Party Wall etc. Act 1996 (legislation.gov.uk) · The Party Wall etc. Act 1996: explanatory booklet (GOV.UK) · Faculty of Party Wall Surveyors (FPWS). Last reviewed 27 October 2026. General guidance on the law in England and Wales, not legal advice.

Frequently asked questions

Which option is cheapest for the building owner?

Consent, then consent with a Schedule of Condition. Awards cost more, and own-surveyor Awards usually cost the most because two surveyors are involved.

Does consent mean the neighbour loses protection?

No. The building owner’s duties under the Act still apply, including avoiding unnecessary inconvenience, protecting the neighbour’s property and making good damage, and if a dispute arises later the procedure can be used then.

Is the neighbour’s own surveyor ‘on their side’?

Every surveyor appointed under the Act must act impartially and consider both owners’ rights. A surveyor chosen by the neighbour is not an advocate.

Can the neighbour change their mind after consenting?

Consent to the notified works is binding for those works, but if a dispute later arises about something connected with them, such as damage, it can be referred to surveyors.

Can I insist on an Agreed Surveyor?

No. The neighbour is entitled to appoint their own surveyor. You can suggest an Agreed Surveyor and explain the benefits.

What does the government booklet recommend?

It says an Agreed Surveyor is preferable in residential cases where surveyors’ fees would significantly increase the project costs.

Is a Schedule of Condition still taken if there is an Award?

Yes, normally. It is usually annexed to the Award.

Who chooses the third surveyor?

The two party-appointed surveyors select the third surveyor in writing, at the outset.

Can I consent to some of the works and dissent to others?

Yes. Each notice is separate, so you can consent to one (for example, cutting in a beam) and dissent from another (for example, excavation under s.6).