Home › Guides › Create your own party wall agreement
Party wall guide

Can I create my own party wall agreement?

Plenty of homeowners handle the first stage of the Party Wall etc. Act 1996 themselves, and the Act allows it. What it does not allow is for either owner to write their own Award if the neighbour disagrees. This guide sets out where DIY works, where it stops, and how to protect yourself if you go it alone.

CB

Written by Carl Brady MFPWS, MPTS

MFPWSMPTS

Party wall surveyor with 25+ years’ experience in party wall matters across the Midlands, Hertfordshire and London. Last reviewed 29 October 2026.

Short answer: Yes, up to a point. You can write and serve your own notices, and if your neighbour consents in writing, that consent is your party wall agreement. But if they dissent or do not reply within 14 days, only surveyors appointed under s.10 can make the Party Wall Award, and you cannot act as surveyor in your own dispute.

“Party wall agreement” is not a document the Act asks you to draft. The Act works through notices, the neighbour’s response and, if there is a dispute, a Party Wall Award made by surveyors. So “creating your own agreement” really means one of two things: serving your own notices and getting written consent, or agreeing terms informally with your neighbour. The first is lawful and common. The second is fine as a friendly record, but it does not replace the Act’s procedure.

What you can lawfully do yourself

  • Check whether the Act applies. Work on the boundary (s.1), work to a party wall or party structure (s.2) and excavation near a neighbour’s building (s.6) are covered. Minor works such as shelves, replastering, rewiring and minor chases for sockets and wiring are not.
  • Identify every owner. Owners include freeholders and leaseholders with more than a year left (s.20). HM Land Registry title registers cost a few pounds each and avoid serving the wrong person.
  • Write and serve the notices. There is no official form. A notice must contain what the Act requires; see our free notice templates and the GOVPUBLINK. You can serve by hand or by post, or by email only if the neighbour has agreed to accept it (s.15).
  • Record the neighbour’s consent. Written consent to a section 3 or section 6 notice means there is no dispute. Keep the signed reply with your copy of the notice. Our party wall agreement template includes a consent wording you can use.
  • Record the condition of next door. You can take your own dated photographs with the neighbour’s permission. A professional Schedule of Condition is more reliable, but a careful joint photo record is far better than nothing.

Where DIY stops: disputes and Awards

If the neighbour dissents, or does not respond within 14 days (s.5, s.6(7)), a dispute is deemed to have arisen and s.10 applies. The owners must either concur in appointing one Agreed Surveyor, or appoint a surveyor each. The Act defines a surveyor as a person who is not a party to the matter (s.20), so neither owner can act as surveyor in their own dispute. The Act does not require a particular qualification, but in practice you want someone who does this work every week, ideally a member of the Faculty of Party Wall Surveyors.

A home-made document signed by both neighbours after a dispute has arisen is not an Award. It may record goodwill, but it does not give either owner the protection of the Act’s dispute procedure, and if things go wrong it is far harder to rely on.

DIY versus using a surveyor

StageCan you do it yourself?What can go wrong
Deciding which sections applyYesMissing a section 6 excavation or a second neighbour
Identifying ownersYesOmitting a joint owner, freeholder or long leaseholder
Writing and serving noticesYesInvalid content, wrong start date, wrong method of service
Neighbour consents in writingYes: keep the signed replyNo record of condition if damage is alleged later
Neighbour dissents or does not replyNo: surveyors must be appointed under s.10Starting work without an Award
Making the AwardNo: only appointed surveyorsA “DIY Award” has no standing under the Act

The risks of going it alone

  • An invalid notice. A notice with the wrong section, the wrong owners or too short a period is not a valid notice. Consent given in response may be challenged, and the notice period may have to restart.
  • No record of condition. Without a Schedule of Condition, cracks that were already there can be blamed on your work, and genuine new damage can be disputed.
  • Starting too early. Work to a party wall before the notice period has run, or before an Award where there is a dispute, is work outside the Act. See what happens if you start work without notice.
  • Sale problems later. Buyers’ solicitors ask for the notice and the consent or Award. Loose paperwork slows a sale; see selling a house during party wall works.

A sensible middle route

Many owners talk to the neighbour first, then let a surveyor prepare and serve the formal notices, which costs £150 + VAT with us for all your neighbours. If the neighbour consents subject to a Schedule of Condition, notices plus a Schedule is £499 + VAT. If there is a dispute, our full package with an Agreed Surveyor Award is £899 + VAT (£999 + VAT in London); the Agreed Surveyor supplement is £50, currently waived. Fees are fixed and invoiced on completion.

Illustrative example: a side-return extension

Owners of an end-of-terrace house want a single-storey side return with a new wall on the boundary. They identify the neighbour from the title register, serve a section 1 notice themselves one month before the start date, and talk it through on the doorstep. The neighbour signs a consent and agrees to a joint photo record of the garden wall. Months later a crack appears in the neighbour’s patio. Because the photos show the area before work started, both owners can see what is new, and the builder makes it good without argument.

This is an illustrative scenario to show how the Act works in practice. It is not a real case, and the outcome on any real project depends on its own facts.

Checklist if you do it yourself

  • Confirm the sections that apply and the notice period for each.
  • Get title registers for your property and every neighbour’s.
  • Use a notice that contains everything the Act requires, with drawings where needed.
  • Serve correctly and keep proof of service and copies.
  • Diary the 14-day response date; silence is a dispute, not consent.
  • If there is a dispute, appoint a surveyor, and do not start that work until the Award is served.
  • Keep the notice, consent or Award with your property records.

Costs with us

ServiceFee + VATinc VAT
Party wall notices (all your neighbours)£150£180
Notices + one Schedule of Condition£499£598.80
Each extra Schedule of Condition£399£478.80
Standalone Schedule of Condition£450£540
Party Wall Award£400£480
Full package (notices, Schedule, Award)£899£1,078.80
Full package, London£999£1,198.80
Agreed Surveyor supplement£50 currently waived£0

Domestic extensions and loft conversions. Fixed fees, invoiced on completion; we take enquiries only, with no online payment. If your neighbour appoints their own surveyor, the building owner normally pays that surveyor’s reasonable fees as well (s.10(13)), and those are set by that surveyor, not by us.

How we can help

We have handled party wall matters on more than 750 projects across London, the South East and the Midlands. Our qualified surveyors prepare valid notices, Schedules of Condition and Awards on fixed fees, invoiced on completion, and can act as Agreed Surveyor for both owners. Call free on 08000 487897, take the 1-minute check or see our fixed fees. More short answers: party wall agreement questions answered.

This guide is general information on the Party Wall etc. Act 1996, which applies in England and Wales. It is written from our surveyors’ practical experience and is not legal advice; for a specific dispute, take advice on your own facts.

Planning work? Take the 1-minute check, see our fixed fees or call free on 08000 487897. We have helped on 750+ projects.

Sources: Party Wall etc. Act 1996 (legislation.gov.uk) · The Party Wall etc. Act 1996: explanatory booklet (GOV.UK). Last reviewed 29 October 2026. General guidance on the law in England and Wales, not legal advice.

Frequently asked questions

Can I write my own party wall agreement?

You can write and serve your own notices, and your neighbour’s written consent is the agreement. If there is a dispute, the Award must be made by surveyors appointed under section 10.

Can I be my own party wall surveyor?

No. The Act defines a surveyor as a person who is not a party to the matter, so neither owner can act as surveyor in their own dispute.

Is a signed letter from my neighbour enough?

If it is clear written consent to a valid notice, yes. Keep it with the notice. A Schedule of Condition is still strongly advisable.

Is there an official party wall agreement form?

No. There is no government form for an agreement. GOV.UK publishes an explanatory booklet and example notice letters, and you can use our free templates.

What if my neighbour agrees verbally?

Verbal agreement is not written consent. Ask for it in writing; without it, a dispute is deemed to arise after 14 days.

Can my builder sort out the party wall agreement?

A builder can help prepare notices, but if there is a dispute an appointed surveyor must make the Award. Make sure notifiable work does not start early.

Does the Party Wall Act apply to your project?

Tell us about your project and a local qualified surveyor from our team will confirm which party wall notices you need and your fixed fee. Nothing to pay until the work is done.

Free callGet a quote