Adjoining owner guide

Agreed Surveyor vs your own surveyor

Once a dispute arises, the Act gives two ways to appoint surveyors. Both produce a legally binding Party Wall Award, and in both the building owner normally pays. The difference is in how many surveyors are involved and what happens if they disagree.

JM

Written by James Metcalf AssocRICS, MFPWS

AssocRICSMFPWS

Party Wall & Residential Property Surveyor with 20+ years’ experience in surveying and property, covering Kent. Last reviewed 27 October 2026.

Short answer: An Agreed Surveyor (s.10(1)(a)) is one impartial surveyor appointed by both owners, often the building owner’s surveyor. It is quicker and cheaper, and suits works where extra terms are needed but relations are good. Appointing your own surveyor (s.10(1)(b)) means two surveyors who select a third; it is the best route for complex or contentious works, poor information, or strained relations. Every surveyor under the Act must act impartially.

The two routes in the Act

Where a dispute arises or is deemed to arise, s.10(1) requires either (a) both parties to concur in the appointment of one surveyor, the Agreed Surveyor, or (b) each party to appoint a surveyor, and those two surveyors to select a third surveyor forthwith. All appointments and selections must be in writing and cannot be rescinded by either party (s.10(2)).

Agreed SurveyorYour own surveyor
Number of surveyorsOne, acting for both ownersTwo, plus a third surveyor selected by them
Who choosesBoth owners agree on the person, often the building owner’s proposed surveyorYou choose yours; the building owner chooses theirs
Who makes the AwardThe Agreed Surveyor alone (s.10(10))Any two of the three surveyors (s.10(10)); usually the two appointed surveyors
If there is disagreementNo internal referral; if the Agreed Surveyor refuses or neglects to act, the process starts again (s.10(3))Either party or surveyor can refer the issue to the third surveyor (s.10(11))
SpeedUsually quickerUsually slower, as two surveyors must exchange and agree
Cost (normally to the building owner)LowerHigher, as two surveyors are paid
Best forModerate works, good relations, good informationComplex or contentious works, basements, underpinning, poor information, strained relations

The Agreed Surveyor

Many building owners propose their own surveyor to act as Agreed Surveyor. This is entirely proper: once appointed under s.10(1)(a), the surveyor acts for neither owner. Their duty is to the Act and to deciding matters impartially. In practice, the Agreed Surveyor will:

  • review the notice, drawings and any structural engineer’s calculations;
  • inspect your property and prepare a Schedule of Condition;
  • draft an Award covering the work, method, working hours, protection, access and making good;
  • serve the Award on both owners;
  • carry out a final inspection and deal with any damage.

If you have particular concerns, for example a delicate ceiling, a kitchen against the party wall, or a home office you need to keep quiet, tell the Agreed Surveyor early so they can address them in the Award. If you are unhappy with the Award you have the same 14-day right of appeal as in any other case (s.10(17)).

Appointing your own surveyor

Under s.10(1)(b) you choose a surveyor you trust. They inspect your property, review the design with the building owner’s surveyor, ask for further information where it is needed, and agree the Award with the other surveyor. Your surveyor is still bound to act impartially, but you have someone who has looked at the proposals from the perspective of your property, which matters most when the risk is real: deep excavation near shallow footings, underpinning, demolishing and rebuilding the party wall, or a building owner who has been slow to provide information.

The third surveyor

The two appointed surveyors must select a third surveyor at the outset. The third surveyor normally takes no part unless called upon. Either owner, or either appointed surveyor, can refer a disputed point to the third surveyor, who will then make an Award on it (s.10(11)). If one of the surveyors refuses to select a third surveyor, the local authority’s appointing officer can make the selection on application (s.10(8)). The third surveyor is a safeguard, not a routine step: in our experience most two-surveyor disputes are resolved without one.

What if one surveyor does not engage?

The Act has firm time limits. If a party-appointed surveyor refuses to act effectively, the other surveyor may proceed ex parte, and an Award made that way is as effective as one made by an Agreed Surveyor (s.10(6)). If they neglect to act for 10 days after a written request, the other surveyor may proceed ex parte on the subject matter of the request (s.10(7)). This is why choosing a responsive, experienced surveyor matters.

Illustrative example: choosing differently on the same street

Two adjoining owners receive notices from the same building owner. Ms E faces a loft conversion with two beam pockets; drawings and calculations are clear, and she gets on well with her neighbour. She concurs in the building owner’s surveyor acting as Agreed Surveyor and an Award is served within three weeks, including set working hours. Mr F, on the other side, faces an excavation 2.5 metres deep for a basement, beside a house with shallow brick footings. He appoints his own surveyor, who asks for a temporary works design and a monitoring regime. The two surveyors agree an Award that requires crack and movement monitoring during excavation. The building owner pays both surveyors’ reasonable fees.

This is an illustrative scenario to show how the Act works in practice. It is not a real case, and the outcome on any real project depends on its own facts.

Questions to ask any surveyor before appointing them

  • Are you a member of the Faculty of Party Wall Surveyors or RICS, and how many party wall matters do you handle?
  • Will you seek your fees from the building owner under s.10(13)? Please confirm in writing.
  • How quickly can you inspect and prepare the Schedule of Condition?
  • Will you inspect during and after the work, and how is that charged?
  • Do you have any connection with the building owner or their contractor? (For an Agreed Surveyor this is normal; for your own surveyor you may prefer someone independent.)

Making the appointment

  1. Reply to the notice in writing, dissenting and either concurring in the named Agreed Surveyor or naming your own surveyor.
  2. Sign a short letter of appointment for your surveyor (all owners should sign).
  3. Send the reply within 14 days, or within 10 days of any s.10(4) request if one has been served.
  4. Let your surveyor arrange the inspection and liaise with the other side.

Further reading: the same choice from the building owner’s side, consent or dissent and appealing an Award.

Key points

  • Both routes produce a binding Award and, normally, the building owner pays.
  • An Agreed Surveyor suits moderate works, good information and good relations.
  • Your own surveyor is best for complex or contentious works, or where relations are strained.
  • All surveyors appointed under the Act must act impartially.
  • Appointments cannot be rescinded, so choose a surveyor who is experienced and responsive.
  • The third surveyor is a safeguard for unresolved points, not a routine step.

A note on timescales

For a party structure notice the building owner must give at least two months’ notice (s.3(2)(a)), and an Award cannot fix a start date earlier than the end of the notice period unless both owners agree (s.10(12)). In our experience an Agreed Surveyor Award for a straightforward loft or beam is often completed within that period. With two surveyors, the exchange of drafts and any requests for further engineering information take longer, so building owners planning complex work should allow more time.

Practical tip: telling the surveyor your concerns

Whichever route you choose, write a short note to the surveyor before the inspection listing what matters to you: rooms that adjoin the work, fragile finishes, a home office, pets, parking, or a garden wall. Surveyors can only deal in the Award with matters connected with the notified work, but within that scope a clear list helps them set sensible terms on protection, hours and making good.

How we can help

We have handled party wall matters on more than 750 projects, acting for building owners and adjoining owners. If you have received a notice, we can prepare a Schedule of Condition of your property, act as Agreed Surveyor for both owners, or act as your own surveyor. In the normal case the building owner pays the reasonable surveyors’ fees, including ours when we act for you (s.10(13)). Call free on 08000 487897 or see your options as a neighbour.

Received a notice and not sure what to do? See your options or call free on 08000 487897. A local qualified surveyor from our team will help.

Sources: Party Wall etc. Act 1996 (legislation.gov.uk) · The Party Wall etc. Act 1996: explanatory booklet (GOV.UK) · Faculty of Party Wall Surveyors (FPWS). Last reviewed 27 October 2026. General guidance on the law in England and Wales, not legal advice.

Frequently asked questions

Is the building owner’s surveyor biased if they act as Agreed Surveyor?

They should not be. Once appointed under s.10(1)(a), they must act impartially between both owners. If you have doubts, you are free to appoint your own surveyor instead.

Who pays for my own surveyor?

Normally the building owner pays your surveyor’s reasonable fees under s.10(13).

Can I change from an Agreed Surveyor to my own surveyor later?

Appointments cannot be rescinded (s.10(2)). Only if the Agreed Surveyor refuses, neglects to act for 10 days after a request, dies or becomes incapable does the process begin again (s.10(3)).

What does the third surveyor do?

The third surveyor decides any point the two surveyors cannot agree, when called upon by either owner or either surveyor (s.10(11)).

Can my surveyor stop the works?

No. Surveyors settle how and when work is done, and can require protective measures, but cannot refuse work the building owner is entitled to do.

Can a friend or relative act as my surveyor?

The Act defines a surveyor as anyone who is not a party to the matter (s.20), so in theory yes. In practice you will be far better served by an experienced party wall surveyor.

Is one route more protective than the other?

Both produce a binding Award. An Agreed Surveyor suits moderate works; your own surveyor is best for complex or contentious works. The right choice depends on the work and the relationship.