I’ve received a party wall notice: what do I do?

A party wall notice is a formal letter, but it is not a threat. It means your neighbour is following the law. This guide explains, from the surveyor’s side of the table, exactly what the notice means, what your options are, and how to reply properly within the time allowed.

JM

Written by James Metcalf AssocRICS, MFPWS

AssocRICSMFPWS

Party Wall & Residential Property Surveyor with 20+ years’ experience in surveying and property, covering Kent. Last reviewed 27 October 2026.

Short answer: Read the notice, check what work is proposed and reply in writing within 14 days. You can consent; consent subject to a Schedule of Condition (recommended and the most popular choice); dissent and agree an Agreed Surveyor; or dissent and appoint your own surveyor. If you do not reply to a party structure (s.3) or excavation (s.6) notice within 14 days, a dispute is deemed to arise and surveyors will be appointed. The building owner normally pays the surveyors’ reasonable fees, including yours.

Receiving a notice can feel unsettling, particularly if you had no idea your neighbour was planning building work. In practice it is good news: the Party Wall etc. Act 1996 gives you, as the adjoining owner, a formal voice in how and when work affecting your property is carried out, a right to compensation if your property is damaged (s.7(2)), and, in most cases, professional help that you do not pay for. The Act does not let you stop lawful work, but it does make sure it is done properly.

Step 1: check that the notice is genuine and complete

A valid notice must identify the building owner and describe the work. Surveyors check notices carefully, because an invalid notice can mean the process has to start again. Look for the following:

  • Who it is from: the name and address of the building owner (s.3(1) for party structure notices). If the property is jointly owned, all owners should be named.
  • Who it is addressed to: every owner of your property. For the Act, an “owner” includes freeholders and leaseholders with more than a year left on their lease (s.20). If you own a flat, the freeholder may have received a separate notice too.
  • What work is proposed: the nature and particulars of the work, in enough detail for you to understand it.
  • When it will start: the proposed start date, which must respect the notice period.
  • Drawings where required: an excavation notice must be accompanied by plans and sections showing the site and depth of the excavation (s.6(6)). A party structure notice involving special foundations must include plans, sections and load details (s.3(1)).

If something is missing or unclear, you can ask the building owner for more information before you decide. Doing so does not stop the 14-day clock, so ask quickly and in writing.

Step 2: understand which type of notice you have

NoticeTypical worksMinimum notice periodIf you do not reply in 14 days
Line of junction notice (s.1)A new wall built on or against the boundary line, for example a new extension wall or garden wallOne month (s.1(2), s.1(5))For a new party wall straddling the boundary, no reply means no consent, so the wall must be built wholly on the building owner’s land (s.1(4)). Disputes are resolved under s.1(8).
Party structure notice (s.3)Work to an existing shared wall: steel beams, loft conversions, chimney breast removal, raising, underpinning, cutting in flashingsTwo months (s.3(2))A dispute is deemed to arise (s.5) and surveyors are appointed under s.10.
Excavation notice (s.6)Digging foundations within 3 metres (or 6 metres for deeper work) of your building, for extensions, basements or new buildsOne month (s.6(5))A dispute is deemed to arise (s.6(7)) and surveyors are appointed.

It is common to receive two or three notices at once, for example a party structure notice for a beam bearing in the party wall and an excavation notice for the new extension’s foundations. Each needs its own reply, although one surveyor or pair of surveyors usually deals with them together in a single Award.

Step 3: decide how to respond

The Faculty of Party Wall Surveyors (FPWS) describes four sensible responses. In our experience the right choice depends on how close and how intrusive the work is, how good the information is, and how well you get on with your neighbour.

OptionWhen it suits
a. ConsentQuick and simple, but there is no Schedule of Condition, so no record of your property before the works.
b. Consent subject to a Schedule of Condition (recommended, most popular)For straightforward works you keep the full protection of the Act, and the Schedule gives clarity for everyone.
c. Dissent and appoint the Agreed SurveyorWhen extra terms need covering, such as working hours, access or further agreements. One impartial surveyor makes a full Award (s.10(1)(a)). The building owner normally pays.
d. Dissent and appoint your own surveyorBest for complex or contentious works, or where relations are strained. Two surveyors agree the Award; the building owner normally pays your surveyor’s reasonable fees (s.10(13)).

The government’s explanatory booklet confirms that consenting does not take away your rights. It means nothing is in dispute at that point. If a problem arises later, for example cracking appears, the dispute procedure in s.10 is still available and surveyors can be appointed then. That is why, for a simple beam or a modest single-storey extension, consent subject to a Schedule of Condition is our recommended route: it is quick, it costs you nothing in the usual case, and it creates the evidence you would need if anything went wrong.

Dissenting is not a hostile act. It simply means the surveyors set out the terms of the work in a Party Wall Award before it starts. Choose an Agreed Surveyor where you would like formal terms on working hours, access, protection or other matters. Appoint your own surveyor where the work is complex or contentious, for example a basement, underpinning, or a neighbour you no longer communicate with. See Agreed Surveyor vs your own surveyor.

Step 4: reply in writing within 14 days

The 14 days begin with the day the notice was served (s.5, s.6(7)). Notices are normally posted first class and deemed served the next day; s.15 sets out the permitted methods of service, including email only where you have said you are willing to accept it (s.15(1A)).

  1. Use the acknowledgement or reply form enclosed with the notice, or write a short letter.
  2. Tick or state clearly which option you choose. If you are appointing a surveyor, name them and give their address.
  3. Sign and date it. Every owner of your property should sign.
  4. Send it to the building owner (or their surveyor if the notice says so) and keep a copy, with proof of posting or the email.

What happens next under each option

Your replyWhat happens nextTypical timescale
ConsentNothing further is required before the notice period ends. Work can start on or after the date in the notice.Notice period only
Consent with Schedule of ConditionA surveyor arranges a visit, photographs and describes your property, and sends a copy to both owners before work starts.Visit of 1 to 2 hours; report normally sent within a few days, with the Award if all matters are agreed
Agreed SurveyorOne surveyor, accepted by both owners in writing (s.10(1)(a)), inspects, records your property and serves an Award on both of you.From a couple of days to 2 to 4 weeks
Own surveyorYour surveyor and the building owner’s surveyor select a third surveyor, agree the Award and serve it on both owners (s.10(1)(b), s.10(14)).From a couple of days to typically 4 weeks

Common problems we see

  • Ignoring the notice. For s.3 and s.6 notices this does not stop anything. A dispute is deemed to arise, and if you then do not appoint a surveyor within 10 days of a written request, the building owner can appoint one on your behalf under s.10(4). See what happens if you do not respond.
  • Consenting with no record. Plain consent is perfectly lawful, but if cracks appear later there is no evidence of what was already there. Disputes about pre-existing damage are among the most common and most avoidable problems in party wall work.
  • Treating the notice as planning. Party wall matters are separate from planning permission and building regulations. Objections to the design or appearance belong with the council, not the party wall process.
  • Choosing a surveyor without agreeing fees. Ask any surveyor you appoint to confirm in writing that they will seek their reasonable fees from the building owner under s.10(13).
  • Appointment cannot be withdrawn. Once a surveyor is appointed in writing, neither owner can rescind it (s.10(2)). Choose carefully.
Illustrative example: a loft conversion next door

Mrs A owns a Victorian terraced house. Her neighbour serves a party structure notice for a loft conversion with two steel beams bearing into the party wall and a raised section of party wall at roof level. The drawings are clear and the contractor is experienced. Mrs A replies within a week, consenting subject to a Schedule of Condition. A surveyor visits, records hairline cracks in her loft bedroom ceiling and a stained chimney breast, and sends the report to both owners. Six months later, after the works, she notices a new crack along the party wall in her landing. Because the Schedule shows that the landing was previously sound, the building owner accepts responsibility and the crack is made good. Had the matter been disputed, surveyors could have been appointed under s.10 to settle it.

This is an illustrative scenario to show how the Act works in practice. It is not a real case, and the outcome on any real project depends on its own facts.

Your checklist

  • Note the date the notice arrived and the 14-day deadline.
  • Check the notice names the building owner, describes the work and gives a start date.
  • Check drawings are enclosed where the notice involves excavation or special foundations.
  • Photograph the rooms and garden areas next to the party wall, as a personal record.
  • Decide your option and, if appointing a surveyor, confirm their fee position first.
  • Reply in writing, signed by every owner, and keep proof of service.
  • If you let your property, tell your tenants: they are adjoining occupiers with their own rights, including notice of entry under s.8.

How we can help

We have handled party wall matters on more than 750 projects, acting for building owners and adjoining owners. If you have received a notice, we can prepare a Schedule of Condition of your property, act as Agreed Surveyor for both owners, or act as your own surveyor. In the normal case the building owner pays the reasonable surveyors’ fees, including ours when we act for you (s.10(13)). Call free on 08000 487897 or see your options as a neighbour.

Received a notice and not sure what to do? See your options or call free on 08000 487897. A local qualified surveyor from our team will help.

Sources: Party Wall etc. Act 1996 (legislation.gov.uk) · The Party Wall etc. Act 1996: explanatory booklet (GOV.UK) · Faculty of Party Wall Surveyors (FPWS). Last reviewed 27 October 2026. General guidance on the law in England and Wales, not legal advice.

Frequently asked questions

Do I have to pay anything if I receive a notice?

Normally no. Where works are solely for the building owner’s benefit, they normally pay the reasonable surveyors’ costs, including your own surveyor’s, under s.10(13). You may contribute if you ask for extra work for your own benefit or the wall needs repair you are partly responsible for.

Can I stop my neighbour’s works?

No. The Act lets you influence how and when the work is done, and gives you a right to compensation for damage, but it does not let you prevent work the building owner is entitled to do.

What if I miss the 14 days?

For s.3 and s.6 notices a dispute is deemed to arise. You can still appoint a surveyor, or agree to an Agreed Surveyor, provided you do so before the building owner makes an appointment on your behalf under s.10(4).

Is the notice valid if it was put through my door?

Usually yes. Section 15 allows notices to be delivered in person, posted to your usual residence, or addressed to “the owner” and left at the premises. Email is valid only if you have said you will accept service that way.

Can I ask for more information before replying?

Yes. Ask the building owner in writing for drawings, structural calculations or a method statement. Ask quickly, because the 14 days keep running.

I own a leasehold flat. Should I reply?

Yes, if your lease has more than a year to run you are an owner under s.20. The freeholder may also have been served, and each owner replies separately.

Does consenting mean I lose my right to claim for damage?

No. The building owner must still compensate you for loss or damage caused by the works under s.7(2), and any disagreement can be referred to surveyors under s.10.

When can the work start?

Not before the notice period ends unless you agree in writing. If there is a dispute, the work should not start until an Award has been served.

Does the Party Wall Act apply to your project?

Tell us about your project and a local qualified surveyor from our team will confirm which party wall notices you need and your fixed fee. Nothing to pay until the work is done.

Free callGet a quote