If you’re digging foundations or a basement near a neighbour’s building, Section 6 of the Party Wall etc. Act 1996 may apply, even if you don’t share a wall. Here’s how the two tests work.

JG

Written by John Greenan

AssocRICSMFPWSACABE

The short answer

You need to serve a Section 6 notice (an “adjacent excavation” notice) at least one month before you start if you plan to excavate:

  • within 3 metres of a neighbour’s building or structure and deeper than the bottom of their foundations, or
  • within 6 metres of it and any part of your excavation would cut a line drawn down at 45° from the bottom of their foundations.

Rule 1: within 3 metres

Measure horizontally from any part of the neighbour’s building or structure. If your excavation, or the foundations you’re putting in it, will go deeper than the bottom of their foundations within that 3 metres, Section 6(1) applies. Most rear extensions next to older houses fall into this category, because modern footings are usually deeper than Victorian or inter-war ones.

Section 6 within 3 metres diagram
Section 6(1): within 3 m and deeper than the neighbour’s foundation. Illustrative, not to scale.

Rule 2: within 6 metres (the 45° line)

For deeper excavations further away, such as basements, imagine a line drawn down at 45° from the bottom of the neighbour’s foundation, starting at the outside face of their wall and running towards your dig. If any part of your excavation within 6 metres would meet that line, Section 6(2) applies.

Section 6 within 6 metres 45 degree diagram
Section 6(2): within 6 m and cutting the 45° line. Illustrative, not to scale.

What the notice must include

  • Whether you propose to underpin or otherwise strengthen or safeguard the neighbour’s foundations.
  • Plans and sections showing the site and depth of the excavation and, where relevant, the site of any building you’re putting up.
  • At least one month’s notice before the excavation starts.

What happens next

Your neighbour has 14 days to respond. If they consent, you can go ahead once the notice period has passed. If they don’t reply within 14 days, a dispute is treated as having arisen, and surveyors are appointed to agree a Party Wall Award. A Section 6 notice lapses if the work hasn’t started within 12 months.

Not sure if your project is caught? Take the 1-minute check or call free on 08000 487897.

Source: Party Wall etc. Act 1996, section 6 (legislation.gov.uk). General guidance only, not legal advice.

Need a Section 6 notice served?

Tell us about your project. A local qualified surveyor from our team will reply, usually the same working day.

No payment online. Fixed fees, invoiced on completion.

Fixed fees

Everyone starts with notices

The rest of the process depends on how your neighbour responds, so you only pay for what’s actually needed. No hourly billing, no travel charges and nothing to pay up front: every fee is fixed and invoiced on completion.

Step 1 · every party wall agreement starts here

Party Wall Notices: £150 + VAT (£180 inc VAT)

One fee covers ALL your neighbours, including Land Registry checks, bespoke notices, explanatory notes, a consent form, a stamped reply envelope and follow-up ‘Ten Day Notices’ if needed.

Get my party wall notices servedFixed fee, invoiced on completion

What happens next depends on your neighbour’s response

Outcome A

Neighbour consents

£150 + VAT
£180 inc VAT · fixed fee, invoiced on completion
  • Your neighbour signs the consent form
  • The consent is your Party Wall Agreement
  • You can proceed with the works
  • We still recommend a Schedule of Condition to protect you
Find out more
Most common outcomeOutcome B

Consents, subject to a Schedule of Condition

£499 + VAT
£598.80 inc VAT · fixed fee, invoiced on completion
55% of all our projects are notices with a Schedule of Condition
Illustration of a surveyor recording an existing crack on a neighbour's internal wall with a tablet and a crack gauge for a Schedule of Condition
  • Notices for all neighbours + Land Registry checks
  • Site inspection of your neighbour’s property
  • Detailed photographic Schedule of Condition
  • Protects you against claims for damage that was already there
  • Each additional Schedule: £399 + VAT (£478.80 inc)
Request a fixed-fee quote
Outcome C

Neighbour dissents: an Award is needed

£899 + VAT
£1,078.80 inc VAT · total, all areas outside London
London & Greater London: £999 + VAT (£1,198.80 inc)
  • Notices for all neighbours + Land Registry checks
  • 1 Schedule of Condition
  • 1 Party Wall Award
  • Sets working hours, access & damage provisions

Agreed Surveyor — we act for both owners

£50 + VAT Currently waived

Total with Agreed Surveyor+ VATinc VAT
Full package£899£1,078.80
London£999£1,198.80

No extra cost while the waiver runs.

70% of our projects use one surveyor acting for both.

Neighbour appoints their own surveyor: our fee stays as shown. Their surveyor’s reasonable fees are normally payable by you and are charged separately.
Domestic extensions & loft conversions only. Excludes basement and commercial projects. Basement or commercial? Request a quote →
Request a fixed-fee quote
Prefer to serve your own notices?

DIY notices at partywall-notices.co.uk

Our sister service, also run by Konstruction (UK) Ltd, helps you prepare and serve your own party wall notices correctly, with templates for Section 1, 3 and 6.

Visit partywall-notices.co.uk ↗
Already served your own notices?

Schedule of Condition only: £450 + VAT (£540 inc)

We’ll record your neighbour’s property before work starts. If an Award is needed later, it can be added for £400 + VAT (£480 inc) per dissenting neighbour.

Request a Schedule of Condition

Not sure how the Act applies to your project? Call free on 08000 487897 for an initial chat of up to 30 minutes.

Does the Party Wall Act apply to your project?

Tell us about your project and a local qualified surveyor from our team will confirm which party wall notices you need and your fixed fee. Nothing to pay until the work is done.

Free callGet a quote