All the key time limits
| Step | Time limit | Source |
|---|---|---|
| Party structure notice (work to a party wall) | At least 2 months before work starts | s.3(2)(a) |
| Line of junction notice (new wall at the boundary) | At least 1 month before work starts | s.1(2), s.1(5) |
| Excavation notice (within 3 m or 6 m) | At least 1 month before excavating | s.6(5) |
| Consent to a s.3 or s.6 notice | Within 14 days, or a dispute is deemed | s.5, s.6(7) |
| Consent to a s.1 wall astride the boundary | Within 14 days, or build wholly on your land | s.1(4) |
| Counter notice by adjoining owner | Within 1 month of the party structure notice | s.4(2)(b) |
| Request to appoint a surveyor | 10 days, then the other party may appoint | s.10(4) |
| Appointed surveyor neglects to act | 10 days after a request, then the other may act ex parte | s.10(7) |
| Notice of entry to the neighbour’s land | At least 14 days (except emergencies) | s.8(4) |
| Appeal against an Award | Within 14 days of service of the Award | s.10(17) |
| Notice lapses if work has not started | 12 months from service | s.3(2)(b), s.6(8) |
| Projecting footings under s.1 | Between 1 and 12 months after service | s.1(6) |
How the periods are counted
The Act generally counts from the day of service. For example, the 14 days under section 5 run from “the day on which the party structure notice … was served”, and the 10 days under section 10(4) begin “with the day on which the other party serves a request”. Notices are normally posted first class and deemed served the next day, so allow for that and keep proof of posting. If you are working to a tight date, hand delivery removes the doubt.
Starting sooner
You can start before the notice period ends only with the neighbour’s written agreement. They are not obliged to agree, even if they consent to the works themselves. Where there is an Award, any period it sets for the work does not begin to run until the statutory notice period has expired, unless the owners agree otherwise (s.10(12)).
Notice periods are minimums, not the whole timeline
If the neighbour consents, the two months may be all you need. If there is a dispute, you need an Award before starting. How long that takes depends on the works, how quickly drawings are available and whether one Agreed Surveyor or two surveyors are involved. For a straightforward domestic job with an Agreed Surveyor, the Award is often in place within the notice period; with two surveyors, or a complex basement, it can take longer. That is why we advise serving notice as soon as you have workable drawings, not when the builder is ready.
Worked example: planning backwards from a start date
Illustrative only. Lucy’s builder can start a rear extension with a loft on 1 June. The loft beams need a section 3 notice; the extension needs section 6. Working backwards:
- Section 3 notice must be served by 1 April at the latest (two months). Section 6 by 1 May, so serve both together by 1 April.
- 14 days later (mid-April) she will know whether the neighbours consent. If one dissents, surveyors are appointed straight away.
- If a neighbour ignores the request to appoint, a further 10 days runs before a surveyor can be appointed for them, taking her into late April.
- That leaves roughly five weeks for the Schedule of Condition and the Award before 1 June.
Serving in early March instead would give a comfortable margin, and the notice would still be valid well beyond the start date.
Typical durations for common projects
| Project | Notices usually needed | Serve at least |
|---|---|---|
| Single-storey rear extension, no work to the party wall | s.6, possibly s.1 | 1 month before |
| Rear extension with a beam or flashing into the party wall | s.6 and s.3 | 2 months before |
| Loft conversion | s.3 | 2 months before |
| Chimney breast removal | s.3 | 2 months before |
| Basement | s.3 and s.6 | 2 months before, realistically more for the Award |
| New masonry garden wall on the boundary | s.1, possibly s.6 | 1 month before |
Emergencies and dangerous structures
Section 3 does not require a party structure notice before you comply with a statutory notice about dangerous or neglected structures (s.3(3)(b)), and notice of entry can be shortened in an emergency to whatever is reasonably practicable (s.8(3)(a)). These are narrow exceptions. Inconvenience or a builder’s schedule is not an emergency.
What if the start date in the notice slips?
The notice states a start date, but it does not oblige you to start then; the important limits are the minimum period and the 12-month lapse. If your project is delayed past 12 months from service, serve fresh notices. If the design changes materially, serve a new or supplementary notice, which restarts the relevant period for that work.
Periods that run after work starts
Some time limits only matter later. Where the adjoining owner has to pay part of the cost of work under section 11, the building owner must serve an account within two months of completion; the adjoining owner then has one month to object, after which they are deemed to have no objection (s.13). If security for expenses has been requested under s.12, it must be given before the relevant work begins. And under section 6, the neighbour can ask for particulars, including plans and sections, of the completed excavation work (s.6(9)).
Common timing mistakes
- Giving a start date in the notice that is less than the minimum period after service.
- Counting from the date written on the notice rather than the date of service.
- Assuming that silence after 14 days means consent; it means a dispute (s.5).
- Making a s.10(4) appointment before the ten days have run.
- Letting the 12 months pass during a planning or funding delay, then starting on a lapsed notice.
Notice periods for flats and multiple owners
Where an adjoining building is split into flats, each owner (the freeholder and each leaseholder with a lease of more than a year, s.20) must be served. Each owner’s 14 days and the notice period run from service on that owner, so if one notice goes out late, your earliest start date for work affecting them moves too. Serve everyone on the same day where you can, and keep a record of when and how each notice was served.
Sources and further reading
- Party Wall etc. Act 1996, section 1: New building on line of junction (legislation.gov.uk)
- Party Wall etc. Act 1996, section 3: Party structure notices (legislation.gov.uk)
- Party Wall etc. Act 1996, section 4: Counter notices (legislation.gov.uk)
- Party Wall etc. Act 1996, section 5: Disputes arising under sections 3 and 4 (legislation.gov.uk)
- Party Wall etc. Act 1996, section 6: Adjacent excavation and construction (legislation.gov.uk)
- Party Wall etc. Act 1996, section 8: Rights of entry (legislation.gov.uk)
- Party Wall etc. Act 1996, section 10: Resolution of disputes (legislation.gov.uk)
- Party Wall etc. Act 1996, section 15: Service of notices etc. (legislation.gov.uk)
- GOV.UK: The Party Wall etc. Act 1996 explanatory booklet
- GOV.UK: Party walls and building work
Section references are to the Party Wall etc. Act 1996 as it applies in England and Wales, checked against legislation.gov.uk. This guide is general professional guidance, not legal advice; every project should be assessed on its own drawings.
- Party wall agreement questions answered
- Party wall notices for building owners
- Party wall agreement surveyor
- Fixed fees: party wall agreement cost
- Do I need a party wall agreement? (1-minute check)
Areas we cover include Party Wall Agreement Sussex · Party Wall Agreement Birmingham · Party Wall Agreement West Midlands and more.
Sources: Party Wall etc. Act 1996 (legislation.gov.uk) · The Party Wall etc. Act 1996: explanatory booklet (GOV.UK). Last reviewed 27 October 2026. General guidance on the law in England and Wales, not legal advice.